Multi-Million Dollar Construction/expansion 7,500-9,500 sqft of data space available - Mid Summer 2019

Under Construction.png

Week of April 29th - May 3rd, 2019   Our bay is cleared out and ready to get underway for a new makeover.

Week of April 29th - May 3rd, 2019

Our bay is cleared out and ready to get underway for a new makeover.


Week of May 6th - May 10th, 2019   Construction is underway. East walls have studs and electrical runs ready for some drywall.

Week of May 6th - May 10th, 2019

Construction is underway. East walls have studs and electrical runs ready for some drywall.


Week of May 13th - May 17th, 2019   Drywall is completed and ready for a fresh painting. Electrical and cooling runs getting completed for under the 3 foot raised flooring.

Week of May 13th - May 17th, 2019

Drywall is completed and ready for a fresh painting. Electrical and cooling runs getting completed for under the 3 foot raised flooring.


Week of May 20th - May 24th, 2019   Paint on drywall is completed, cooling runs are completed and next week flooring starts getting put in.

Week of May 20th - May 24th, 2019

Paint on drywall is completed, cooling runs are completed and next week flooring starts getting put in.


Week of May 27th - May 31st, 2019   The room is starting to come together. 3 feet of raised flooring is being added and should be completed the first week of June.

Week of May 27th - May 31st, 2019

The room is starting to come together. 3 feet of raised flooring is being added and should be completed the first week of June.


Week of June 3rd - June 7th, 2019   Almost two weeks of construction and the flooring is complete.

Week of June 3rd - June 7th, 2019

Almost two weeks of construction and the flooring is complete.


Week of June 10th - June 14th, 2019   Fire protection Vesda (Very Early System Detection Agent) and electrical for lighting being installed.

Week of June 10th - June 14th, 2019

Fire protection Vesda (Very Early System Detection Agent) and electrical for lighting being installed.


Week of June 17th - June 21st, 2019   Power supply/breaker boxes, uninterupted power supplys, cooling/air conditioning and ceiling grid being installed.

Week of June 17th - June 21st, 2019

Power supply/breaker boxes, uninterupted power supplys, cooling/air conditioning and ceiling grid being installed.


Week of June 24th - June 28th, 2019   Ceiling gride complete, lighting set into place and ready for ceiling tiles.

Week of June 24th - June 28th, 2019

Ceiling gride complete, lighting set into place and ready for ceiling tiles.


Week of July 1st - July 5th, 2019   We are ahead of schedule! Construction is nearly complete and we should be ready by the end of next week. Just need to put a good spit shine on things and we will be ready to start adding cabinets to this multi-million dollar addition. Customers are ready and we can’t wait. Very Exciting!!

Week of July 1st - July 5th, 2019

We are ahead of schedule! Construction is nearly complete and we should be ready by the end of next week. Just need to put a good spit shine on things and we will be ready to start adding cabinets to this multi-million dollar addition. Customers are ready and we can’t wait. Very Exciting!!


Unveiling.png